The correct sequence for setting up a traffic control zone begins with identifying the work zone. This initial step is crucial as it establishes the specific area that will require traffic control measures. Understanding the scope and nature of the work ahead allows for an appropriate traffic control plan to be developed, which outlines how to manage traffic safely around the site.

After the work zone is identified, developing the traffic control plan is essential. This plan must consider various factors, such as the type of work being done, traffic volume, speed limits, and any potential hazards. A well-thought-out plan ensures that the traffic control devices used will effectively protect both the workers and the traveling public.

Once the traffic control plan is in place, the next step is to set up the traffic control devices as detailed in the plan. Proper placement of signs, cones, and barriers is critical to communicate the necessary information to drivers and pedestrians clearly.

Lastly, monitoring the traffic control zone is necessary to ensure that the devices remain effective and that the traffic flow is safe. This involves observing the area for compliance with the setup and making adjustments as necessary.

Thus, the sequence of identifying the work zone, developing a traffic control plan, setting up devices, and monitoring reflects the essential steps to ensure safety and